EskomRBI Project

 

NEC3 Professional Services Contract (PSC3)

between

Eskom Holdings SOC Limited

and

Steinbeis Advanced Risk Technologies GmbH

for

 The Implementation Partner for the Risk Based Inspection programme at Eskom Head Office (MEGAWATT PARK) and 13 Power Stations

 
 
Project Description
 
 
Acronym: ESKOM-RBI
Start date: January 15, 2013
End date: July 14, 2017
Total project value: approx. 4M€
Project coordinator: A. Jovanovic
Total number of partners: 2
Contact person (name/email): eskomrbirisk-technologies.com
Project webpage R-Tech/EU-VRi: www.eskomrbi.risk-technologies.com
 
   
 
SD&L
 
Map
     Map View: Eskom Power Stations
     Legend